15th & Santa Fe Intersection Reconstruction to Begin on Tuesday, June 25

15th and Santa Fe Reconstruction Map - June 2019

Beginning on Tuesday, June 25th, contractors will reconstruct the concrete intersection located at 15th Street and Santa Fe Avenue.  The project will last approximately seven weeks with cooperative weather and has a scheduled completion date of August 12th.

During the work, traffic will be reduced to one lane in all directions and driveways will be closed periodically.  Traffic signals will be reprogrammed to allow one direction proceed at a time in order to allow for safe left turns.  Motorists should expect significant delays when traveling through the intersection and are encouraged to find an alternate route if possible.

The contractor for the project is A-Tech Paving. The total cost of the intersection reconstruction is $796,240.00.

###