Posted on: July 31, 2020

Covell Road Closure Set for Phase II of Widening Project

Covell Widening - May 2020

Beginning on Friday, August 7th, a full closure of Covell Road will be required between Griffin Boulevard and Lamond Hill Avenue.  The closure is expected to last through the early part of December while contractors install storm sewer structures under the roadway.  

Local traffic will be able to access their property from the appropriate side, but thru traffic will not be allowed to pass during this time.  Those wishing to access the following roads will need to access them from the appropriate direction:

•    Access from West (Coltrane): Griffin Park Boulevard, Covell Lane & Loire Valley Drive

•    Access from East (Sooner): Lamond Hill Avenue, Shelburne Drive & Fairfax Boulevard

Crossland Heavy Construction is the contractor for the full 260 day widening project at a total cost of $9,636,281.78. 

###