Future Construction Projects
The following projects are under constant review and may be moved up or down in the scheduling depending on availability of funding and local priorities. 

Danforth Widening, Thomas to Fretz & Thomas Widening, Danforth to Covell
This project will widen Danforth to a five lane roadway with a left turn lane into Edmond North High School and widen Thomas to a three lane roadway with turn lanes into both the North High School as well as John Ross Elementary. The project includes a signal light at Danforth and Thomas.  

The City will apply for 80% Federal funds with 20% City funds. Estimated construction cost is $5,367,374.02. The anticipated start date is unknown at this time. 

15th and Broadway
This project will evaluate the existing lane capacity to determine where additional lanes are needed. Signal light modifications will accommodate any changes in the lane configurations. This project is part of the 2000 Sales Tax Improvements.

The estimated construction cost is $495,939.00. The funding split is 72% Federal funds and 28% City funds. The anticipated start date is unknown at this time.

33rd Street, Coltrane to I-35

This project consists of widening 33rd Street to provide for a four lane divided roadway with left turn lanes at the side streets. The center median will be landscaped. The project will also include multi-use paths/sidewalks.

This project is part of the 2000 Sales Tax Improvements. The estimated construction cost is $3,911,046.26. The funding split will be 80% Federal funds and 20% City funds. The anticipated start date is unknown at this time.

Danforth and Kelly
This project will widen the intersection to a four lane divided road with dual left turn lanes and separate right turn lanes. The project extents will be approx 1400 feet east, west and south and 500 feet to the north.

The estimated cost is $4,269,695.31.  The City will apply for 80% Federal funds with 20% City funds. The anticipated start date is unknown at this time.

Covell, Santa Fe to West City Limits
This project will widen Covell to provide for a four lane divided roadway. There will be left turn lanes at all side streets. Covell will also include street lighting, bike paths and landscaping. Several new bridge structures will be required at the Santa Fe intersection.

The estimated construction cost is $5,500,000. The City will apply for 80% Federal funds with 20% City funds. The anticipated start date is unknown at this time.  

Kelly, Coffee Creek to Waterloo
This project will widen Kelly to a four lane divided roadway with left turn lanes at all side streets. The mile section from Sorghum Mill to Waterloo will not be divided. A signal light will be constructed at the intersections of Coffee Creek, Mesa Trail (Cross Timbers Elementary School), and Sorghum Mill Road. The project will also include street lighting and landscaping from Coffee Creek to Sorghum Mill.
 
The estimated construction cost is $7,000,000.00. The City will apply for 80% Federal funds with 20% City funds. The anticipated start date is unknown at this time.

Sooner Road Bridge Replacement, 0.6 Miles North of Covell Road
This project will replace the existing bridge with a four lane bridge with sidewalks on both sides of the bridge and a trail underpass on both ends alongside Coffee Creek to accommodate the trails system. 

The estimated construction cost is $2,402,561.19. The City will apply for 80% Federal funds with 20% City funds. The anticipated start date is unknown at this time.

2nd and Bryant
This project consists of adding dual left turn lanes for all four directions as well as a single right turn lane for all four directions. New signal lights will be included. This project is part of the 2000 Sales Tax Improvements.

The estimated construction cost is $3,811,731.86. The funding split and anticipated start date is unknown at this time.

33rd and Technology Dr.
This project will add left and right turn lanes on 33rd Street as well as a new signal light.

The estimated construction cost is $2,250,000.00. The City will apply for 80% Federal funds with 20% City funds. The anticipated start date is unknown at this time.

Phase 2, Intelligent Transportation System Broadway, Danforth, Covell, Santa Fe Corridor Project
This project consists of installing fiber optic cable and replacing the traffic signal cabinets and controllers and associated signal equipment at 26 intersections on Broadway - 9th to Comfort, Danforth – Boulevard to Sherry, Santa Fe – Covell to Danforth and Covell – Broadway to Marilyn Williams in order to bring them into compliance with the National Transportation Communication for Intelligent Transportation System Protocol (NTCIP) standards. These intersections will connect to the Traffic Management Center via fiber optics and wireless communication network. 

The estimated construction cost is $2,947,625. The City will apply for 80% Federal funds with 20% City funds. The anticipated start date is unknown.

Covell, Broadway to Fairfax
This project will widen Covell to provide for a four lane divided roadway where possible. There will be left turn lanes at all side streets where possible. Covell may also include street lighting, 10 foot wide multi-use paths/sidewalks, and landscaping.

The project is currently under design however, no construction funding is identified at this time. The estimated construction cost is unknown at this time. 



Engineering Department
Steve Manek
Director of Engineering

10 S. Littler Ave.
Edmond, OK 73034
View Map

Ph: (405) 359-4770
Fax: (405) 359-4696

Hours
Monday - Friday
8:00 am - 5:00 pm
Help Center